MEDIA CONTACT: Misti Guertin, Communications and Digital Media Manager
(772) 600-1250, mguertin@ci.stuart.fl.us
FDOT sr-76/KANNER HIGHWAY RESURFACING PROJECT UPDATE
Weekend Double-Lane Closures on Southbound SR-76/Kanner Hwy from S. Manor Drive to Seville Street
8:30 p.m. Friday through 6 a.m. Monday - April 14-17; April 21-April 24; April 28-May 1; May 5 -8, 2023
UPDATE: Two southbound SR-76/Kanner Highway travel lanes between S Manor Drive and SE Seville Street will be closed around-the-clock from 8:30 p.m. Friday night, April 14, through 6 a.m. Monday morning, April 17, for drainage work. The weekend double-lane closures will continue to occur April 21-24, April 28-May 1, and May 5-8. Please see below for more traffic impact information,
State Road 76/Kanner Highway Resurfacing Project
Description: This 1.4-mile resurfacing project from north of Cabana Point Circle to SR 5/U.S. 1 in the City of Stuart will began on Monday, July 25, 2022. Project improvements include milling and resurfacing the existing roadway; some minor widening will occur along northbound and southbound SR 76/Kanner Highway; upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards; installing sidewalks, signage and pavement markings; upgrading pedestrian lighting at two signalized intersections at SR 714/Monterey Road and SR 5/U.S. 1; and, upgrading or restoring drainage pipes and replacing sections of the City of Stuart’s watermain at various locations.
Cost/Completion: $5,064,094.62. Completion is expected summer 2023.
Traffic Impact:
- The sidewalk on southbound SR 76/Kanner Highway between SR 5/U.S. 1 and SR 714/Monterey Road is closed through April 2023 to facilitate roadway and drainage work. Pedestrians are directed to use the signalized crossings at the intersections of SR 714/Monterey Road and SR 5/U.S. 1 to access the sidewalk on northbound SR 76/Kanner Highway.
- One southbound outside lane of SR 76/Kanner Highway from the Monterey Road intersection to SR 5/U.S. 1 may be closed around the clock through Friday, April 28, for drainage, utility, sidewalk, and lighting work.
- One northbound outside lane of SR 76/Kanner Highway from the parking entrance to Water’s Edge Dermatology south of the Monterrey Road intersection to SE Lonita Street will be closed from 8 a.m. to 4 p.m. as needed, through Friday, April 28, for lighting, signalization, and site restoration work.
- Two northbound outside lanes of SR 76/Kanner Highway from the Monterey Road intersection to SR 5/U.S. 1 will be closed nightly from 8 p.m. to 6:30 a.m. through Friday, April 28, for lighting work and milling and resurfacing the roadway.
- Two southbound lanes of SR 76/Kanner Highway from the intersection of Monterey Road to SR 5/U.S. 1 will be closed nightly Monday through Friday, through Friday, April 28, from 8 p.m. to 6:30 a.m. for drainage, utility, sidewalk, and lighting work.
- One westbound lane of SR 714/SW Monterey Road from the Monterey Shopping Plaza driveway to the European Kitchen and Bath driveway may be closed from 8 a.m. to 4 p.m., as needed, through Friday, April 28, for lighting, foundation work.
- One eastbound lane of SR 714/SW Monterey Road from the Riverwatch Marina to the WAWA driveway entrance will be closed from 8 a.m. to 4 p.m. as needed, through Friday, April 28, for lighting work.
- One northbound lane of SR 76/S Kanner Highway from SR 5/U.S. 1 to Seacoast Bank Court will be closed from 8 a.m. to 6:30 p.m. as needed, through Friday, April 28, for lighting and foundation work.
- One northbound inside lane of SR 76/Kanner Highway from SR 5/U.S. 1 will be closed from 8 a.m. to 6:30 p.m. as needed through Friday, April 28, for signage installation work.
- One eastbound lane of SR 5/U.S. 1 from the Citgo Gas Station in front of the Twin Plaza Shopping Center to the first driveway entrance to Bank of America Financial Center will be closed from 8 a.m. to 4 p.m. as needed, through Friday, April 28, for lighting work.
- Two southbound lanes of SR 76/Kanner Highway from S Manor Drive to SE Seville Street will be closed around-the-clock from 8:30 p.m. Friday night through 6 a.m. Monday morning on the following dates for drainage work:
- Friday night, April 14 through Monday morning, April 17
- Friday night, April 21 through Monday morning, April 24
- Friday night, April 28 through Monday morning, May 1
- Friday night, May 5 through Monday morning, May 8
For more information on the FDOT projects, please contact The Corradino Group, Community Outreach Specialist Samantha Kayser at (772) 579-5479.